数字化转型助力全球首个可持续铁矿石工厂建设

分类工业科技
事件时间近期
地点巴西维多利亚
来源CP
发布时间2026/04/21 12:01
详情描述
近期,德勤与淡水河谷在巴西维多利亚成功建成全球首个铁矿石压块工厂。该项目总投资额为3.4亿美元,是全球钢铁行业脱碳进程中的重要设施,其生产的铁矿石产品可将钢铁生产过程中的二氧化碳排放量降低最多10%。
在建设过程中,项目团队应用了Bentley Systems的数字化工具,通过SYNCHRO 4D技术创建了施工过程的“数字孪生”,在物理施工开始前即在虚拟空间内完成全流程模拟。该系统协助管理人员对1500多个工作包进行了精准协调,并识别并消除了超过2000个施工限制,在提升施工安全性的同时缩短了工期。
此外,项目还集成了iTwin Capture无人机影像技术与Cesium地理测绘系统,实现了对施工现场进度的实时监控。数据显示,数字化工具的应用使项目进度准确性提升了41%,工程审批时间缩短了10天。该项目此前入围了Bentley基础设施年度奖项(YII)及数字化转型奖项决赛。
📋 简要摘要 ▸
德勤与淡水河谷在巴西维多利亚成功建成全球首个铁矿石压块工厂。该项目投资3.4亿美元,通过Bentley Systems的SYNCHRO 4D等数字化工具创建“数字孪生”,实现了施工过程的精准模拟与协调。此举不仅消除了2000多个施工限制,提升了安全性,还将进度准确性提高了41%,显著推动了钢铁行业的脱碳进程。
📋 完整原文 ▸
[来源: CP] [分类提示: NEWS]
标题: Digital Transformation Powers World’s First Sustainable Iron Ore Plant
Deloitte and Vale have recently successfully completed the world’s first iron ore briquette plant in Vitória, Brazil, utilizing digital tools from Bentley Systems. The project was also one of the finalists of Bentley Year in Infrastructure (YII) and the Going Digital Awards.
This $340 million facility is a cornerstone of global decarbonization efforts, producing a specialized iron ore product that can slash carbon dioxide emissions in steelmaking by up to 10%, transforming the complex construction site into a high-tech digital environment.
One of the most important tools used in this project is SYNCHRO 4D. By creating a “digital twin” of the construction process, the team could visualize the entire build in a virtual space before physical work even began.
This allowed managers to coordinate more than 1,500 different work packages with extreme precision. This digital twin also helps identify and remove over unexpected 2,000 construction constraints, which didn’t just save time but significantly boosted worker safety.
Besides, by integrating iTwin Capture to pull in drone imagery and Cesium for geographical mapping, the team maintained a constant, real-time view of the site’s progress. Using this tool, schedule accuracy jumped by 41%, and the time required for engineering approvals was cut by 10 days.
Using AI-powered tools alongside Bentley’s data, the team can also reduce the time spent on report