巴萨河大桥工程进度达73% 预计连接铁桥头区与百列区

分类基建
事件时间2026-05-31
地点金边
来源CP
发布时间2026/06/04 09:50
详情描述
截至2026年5月底,连接金边铁桥头区(Chak Angre Krom)与百列区(Prek Pra)的巴萨河大桥项目整体进度已达73%。该项目自2024年2月19日正式动工以来,工程进展顺利。
2026年6月1日,由柬埔寨国务秘书兼项目总监Soung Heng率领的考察组前往现场视察,并确认桥梁梁体已全部完成从西岸至东岸的运输工作。目前,施工人员正进行混凝土浇筑作业,以加固桥梁连接部分。
在工程细分进度方面,大桥基础及下部结构已完成100%,连接桥的上部结构也已完工。主桥上部结构目前完成约67.30%,其中右侧箱梁计划的49个节段中已完成36个,左侧箱梁49个节段中已完成30个。
此外,大桥配套道路网络的整体进度为48.40%。具体包括全长804.30米的连接道路已完成50%,全长1.54米的匝道工程已完成46%。
📋 简要摘要 ▸
连接铁桥头区与百列区的巴萨河大桥项目进展顺利,截至2026年5月底已完成73%。目前桥梁基础及下部结构已完工,主桥上部结构完成约67%,配套道路网络完成约48%。项目自2024年2月动工以来,目前已完成全部桥梁梁体运输,正进行混凝土浇筑作业。
📋 完整原文 ▸
[来源: CP] [分类提示: NEWS]
标题: Construction of Bassac River Bridge Linking Chak Angre Krom and Prek Pra Reaches 73% Completion
The construction of the highly anticipated bridge across the Bassac River, connecting Chak Angre Krom to Prek Pra, has achieved a major milestone, reaching 73% completion by the end of May 2026. According to the inspection team on 01 June 2026, led by HE Soung Heng, Secretary of State and Project Director, to monitor the progress of the site and witness the successful completion of transporting bridge beams from the west bank to the east bank. This vital infrastructure project has maintained steady momentum since its official groundbreaking ceremony on 19 February 2024.
A detailed breakdown of the project showcases excellent engineering progress across all phases. Both the bridge foundation and the substructure have reached 100% completion, alongside the upper structure of the connecting bridge. Meanwhile, the upper structure of the main bridge is currently evaluated at 67.30% percent complete. Out of 49 segments planned for the right-hand box girder, 36 have been completed, while 30 segments out of 49 have been finalized for the left-hand box girder. For the surrounding road network, overall progress stands at 48.40%, with the 804.30m connecting road hitting the 50% mark and the 1.54m ramp road reaching 46% completion.
The transportation of all 96 bridge beams from the west bank to the east bank is now complete, and workers are actively pouring concrete to secure the connect