柬埔寨5号公路改造工程最后路段进度过半

分类基础设施
事件时间2026年4月
地点柬埔寨班迭棉吉省
来源CP
发布时间2026/04/20 09:59
详情描述
柬埔寨5号公路改造工程迎来重要节点,连接班迭棉吉省诗梳风市至波贝市的最后路段施工进展顺利。截至2026年4月上旬,该路段全长35.14公里的改造工程已完成51.07%。
柬埔寨公共工程与运输部发言人彭林于2026年4月9日确认了上述进度。该项目于2023年11月22日正式动工,总投资额为5256万美元,资金由柬埔寨政府预算及日本政府提供的信贷支持共同构成。工程旨在提升道路质量并扩大通行能力,使其达到国际标准。
按照施工计划,该项目预计于2027年完工。作为连接泰国边境的关键贸易通道,该路段在提升物流效率与跨境交通方面具有重要作用。目前施工现场作业繁忙,交通部门提醒过往司机在经过施工路段时务必注意行车安全。
📋 简要摘要 ▸
柬埔寨5号公路诗梳风至波贝路段(全长35.14公里)改造工程进展顺利,截至2026年4月上旬已完成51.07%。该项目由柬日合作投资5256万美元,预计2027年完工。作为连接泰国的关键贸易通道,交通部提醒过往司机在施工路段注意行车安全。
📋 完整原文 ▸
[来源: CP] [分类提示: NEWS]
标题: Final Stretch of National Road 5 Renovation Surpasses Halfway Mark
Strategic 35-kilometer link between Serey Sophorn and Poipet targets 2027 completion as joint Cambodian-Japanese project enters critical phase
The comprehensive rehabilitation of Cambodia’s National Road 5 has entered its final stages, with the segment connecting Serey Sophorn and Poipet now more than 51 percent complete. This progress update, reflecting data from the first week of April 2026, marks a significant milestone for the 35.14-kilometer infrastructure project in Banteay Meanchey province.
Speaking on April 9, 2026, Mr. Phorn Rim, Spokesperson for the Ministry of Public Works and Transport, confirmed that the overall work on this final section has reached 51.07 percent. The project is currently on track to meet its 2027 deadline, providing a modernized transportation artery that is expected to facilitate trade and travel toward the Thai border.
This final 35.14-kilometer stretch represents a substantial investment of 52.56 million US dollars, funded through a combination of the Cambodian government’s budget and credit assistance from the Japanese government. Since construction began on November 22, 2023, teams have been working intensively to upgrade the road quality and expand its capacity to meet international standards.
As the construction sites remain active and busy, Ministry officials have issued an appeal to all motorists to exercise extreme caution when traveling along the affected rou