暹粒供水与卫生项目进度超90% 污水处理系统即将完工

分类基础设施
地点暹粒
来源CP
发布时间2026/06/12 08:30
详情描述
2026年6月1日,暹粒供水与卫生改善项目核心合同包进度已超过90%。污水处理系统管理局局长兼项目总监Chao Sopheaphibal率队对项目现场进行了视察。
参与此次视察的代表包括暹粒省污水管理单位、项目咨询联合体(CTI Engineering International Co., Ltd.与PPIC Co., Ltd.)、中铁二局集团有限公司,以及Phkay Prek与Jace Korea联合体施工团队。技术专家组随行对公用基础设施的运营标准进行了评估。
此次实地考察重点检查了城市升级的关键组成部分,包括支线及侧向污水管网的铺设、居民污水连接的整合,以及暹粒河东西两岸两座新建污水泵站的建设情况。此外,考察组还评估了作为基础设施修复工程一部分的新建混凝土道路施工进度。
根据官方项目数据,该工程旨在提升暹粒城市基础设施标准,改善当地居民生活环境及旅游配套设施,为城市提供更稳定的供水与排水服务。
📋 简要摘要 ▸
暹粒供水与卫生改善项目核心合同包已完成超90%。项目包括铺设支线污水管网、建设暹粒河东西两岸污水泵站及配套道路修复。该工程旨在提升暹粒城市基础设施标准,改善居民生活环境及旅游配套设施。
📋 完整原文 ▸
[来源: CP] [分类提示: NEWS]
标题: Siem Reap Sanitation and Water Supply Project Achieves Major Milestones
The Water Supply and Sanitation Improvement Project in Siem Reap City has made substantial progress, with core contract packages now exceeding ninety percent completion. The advancement was highlighted during an on-site inspection on June 1, 2026, led by Chao Sopheaphibal, the Director General of the General Department of Wastewater Treatment System and project director.
The delegation for the inspection included representatives from the Siem Reap Provincial Wastewater Management Unit, the project consulting joint venture of CTI Engineering International Co., Ltd., and PPIC Co., Ltd, alongside construction teams from China Railway No.2 Engineering Group Co., Ltd., and the Phkay Prek and Jace Korea-Joint Venture. Technical experts also joined the tour to review the operational standards of the developing utility infrastructure.
The field visit aimed to monitor several vital components of the urban upgrade, focusing heavily on the installation of sub-branch and lateral sewer lines, the integration of residential wastewater connections, and the development of two new sewage pumping stations located on the eastern and western banks of the Siem Reap River. Additionally, the team assessed the construction of new concrete roads being paved as part of the broader infrastructure restoration.
According to official project data, the scope of the development is divided into specific work packages. Contract pac